Improve mobility and connectivity for people who walk, bike, use transit, and drive.
Lead for Construction: City of Durham Public Works
Lead for Design: City of Durham Transportation
Design Contractors: Kittleson & Associates and Three Oaks Engineering
Scroll down for upcoming engagement opportunities and sign up for updates! Project DescriptionThe City of Durham will resurface approximately 1.10 miles of Stadium Drive from Horton Road to Carver Street. Resurfacing helps improve and preserve current roadway pavement conditions.
During this process, the City can adjust current pavement marking designs on the road and install traffic calming features to increase safety for all road users. For example, on some roads, you can improve or add painted bike lanes and crosswalks, but this project will not allow you to address needs beyond the width of the road, such as building a new sidewalk.
This roadway resurfacing design project will develop pavement marking designs that the City will install after construction. The designs will be based on current conditions and community input.
FundingPlanning and design for the Stadium Dr. roadway resurfacing project is City-funded through the Capital Improvement Plan.
Project map note: project limits are highlighted in yellow with start and end points labeled in blue. Key points of interest are noted with red stars.
PROJECT SCHEDULE- Engagement: March - April 22, 2024
- Anticipated Design Completion: July 2024
- Construction: Due to weather, the City of Durham pavement marking construction season goes from May through November. Construction is anticipated to begin and be completed between these months. For more information regarding construction, visit Public Works Street Repaving.
A design team - Kittleson & Associates and Three Oaks Engineering - was hired by the City of Durham to conduct field investigation and traffic analyses, develop design plans, and hold engagement meetings with the public. City staff kicked off the project in January. The design team is currently collecting data and developing pavement designs. The City will post designs and project updates on this webpage.
community engagementCity staff will host a pop-up event to discuss possible pavement marking changes for Stadium Dr. Planners and engineers will attend this event to explain the work, gather feedback, and answer questions.
Public engagement is open through April 22nd. Design plans and project updates will be added to this webpage. Sign up to the email listserv with the form below to receive regular project updates.
Interactive Comment MapSubmit Stadium Dr. comments on this interactive web map by 4/22/2024.
The public can drop by anytime during the scheduled pop-up event. A Spanish interpreter and other language assistance services will be accessible by phone at the pop-up event. Please contact [email protected] if other language assistance or accommodations are needed.
LocationDateTimeEarth Day Festival, Transportation Expo (Central Park, 501 Foster St)Sunday, April 21, 2024 9:00 AM to 6:00 PM